Site Visit and familiarisation with the Project Constraints and Risks including meetings with the Contracting Teams.
Review of developing design and construction strategy in Stage 1 with particular emphasis on Earthworks/Pavement/Structures/Prelims.
Identified and Developed Risks & Opportunities Register.
Assessed the soft ground earthworks solutions of vertical drainage, dig & replace and piling for the various areas. Reviewed the Earthworks/Structures interface in the soft ground areas against the phasing of the works.
Assessed Traffic Management Strategy. Reviewed the Employers Requirements provided input to further development including integration of the Environmental Commitments.
Digitisation of Geotechnical Information to Google Earth with background mapping to assist with the identification of residual GI required to inform the Target Cost.