Site Visit, Inspection and Examination of the Site and its surroundings and familiarisation with the Project Constraints and Risks that Influenced the Tender Price.
Detailed Pricing of Employers Bill of Quantities (BOQ) based on Employers Design with Build-up of Prices in terms of Labour, Plant, Materials and Productivities / Outputs and Benchmarked with Market Rates.
Developed Alternative Earthworks Priced BOQ including Take-off based on Contract Drawings and Existing Geotechnical Investigation.
Identified and Developed Priced Risk and Opportunities Register.
Developed Execution Strategy Plan which Underpinned the BOQ, Preliminaries , Construction Methodologies and the Programme.
Developed Traffic Management Strategy and Arrangements to Comply with the Work Information and Minimise Traffic Disruption.
Review and Supported the Technical Quality Submission Developed by the Client.